Introduction to Operations ResearchCD-ROM contains: Student version of MPL Modeling System and its solver CPLEX -- MPL tutorial -- Examples from the text modeled in MPL -- Examples from the text modeled in LINGO/LINDO -- Tutorial software -- Excel add-ins: TreePlan, SensIt, RiskSim, and Premium Solver -- Excel spreadsheet formulations and templates. |
From inside the book
Results 1-3 of 28
Page 519
T ( c ) Find the approximate probability that the project will finish within 100
weeks . ( d ) Is the approximate probability obtained in part ( c ) likely to be higher
or lower than the true value ? Optimistic Estimate Most Likely Estimate Activity ...
T ( c ) Find the approximate probability that the project will finish within 100
weeks . ( d ) Is the approximate probability obtained in part ( c ) likely to be higher
or lower than the true value ? Optimistic Estimate Most Likely Estimate Activity ...
Page 522
Therefore , he and the top management of 21st Century Studios have concluded
that they must accelerate production of their movie and bring it out at the
beginning of the summer ( 15 weeks from now ) to establish it as THE movie of
the year .
Therefore , he and the top management of 21st Century Studios have concluded
that they must accelerate production of their movie and bring it out at the
beginning of the summer ( 15 weeks from now ) to establish it as THE movie of
the year .
Page 523
START FINISH FINISH Activity Estimated Duration Estimated Cost Activity
Estimated Duration Estimated Cost 6 weeks 2 weeks 4 weeks 5 weeks 7 weeks 9
weeks $ 420 , 000 $ 180 , 000 $ 540 , 000 $ 360 , 000 $ 590 , 000 $ 630 , 000 23
- as ...
START FINISH FINISH Activity Estimated Duration Estimated Cost Activity
Estimated Duration Estimated Cost 6 weeks 2 weeks 4 weeks 5 weeks 7 weeks 9
weeks $ 420 , 000 $ 180 , 000 $ 540 , 000 $ 360 , 000 $ 590 , 000 $ 630 , 000 23
- as ...
What people are saying - Write a review
User Review - Flag as inappropriate
i
User Review - Flag as inappropriate
I want review this book
Contents
SUPPLEMENT TO APPENDIX 3 | 3 |
Problems | 6 |
An Algorithm for the Assignment Problem | 18 |
Copyright | |
57 other sections not shown
Other editions - View all
Common terms and phrases
activity additional algorithm allocation allowable amount apply assignment basic solution basic variable BF solution bound boundary calculations called capacity changes coefficients column complete Consider constraints construct corresponding cost CPF solution demand described determine direction distribution dual problem entering equal equations estimates example feasible FIGURE final flow problem Formulate functional constraints given gives goal identify illustrate increase indicates initial iteration linear programming Maximize million Minimize month needed node nonbasic variables objective function obtained operations optimal optimal solution original parameters path plant possible presented primal problem Prob procedure profit programming problem provides range resource respective resulting revised Select shown shows side simplex method simplex tableau slack solve step supply Table tableau tion unit values weeks Wyndor Glass zero