Introduction to Operations ResearchCD-ROM contains: Student version of MPL Modeling System and its solver CPLEX -- MPL tutorial -- Examples from the text modeled in MPL -- Examples from the text modeled in LINGO/LINDO -- Tutorial software -- Excel add-ins: TreePlan, SensIt, RiskSim, and Premium Solver -- Excel spreadsheet formulations and templates. |
From inside the book
Results 1-3 of 75
Page 517
Using the PERT three - estimate approach , the three estimates for one of the
activities are as follows : optimistic estimate 30 days , most likely estimate 36
days , pessimistic estimate 48 days . What are the resulting estimates of the mean
and ...
Using the PERT three - estimate approach , the three estimates for one of the
activities are as follows : optimistic estimate 30 days , most likely estimate 36
days , pessimistic estimate 48 days . What are the resulting estimates of the mean
and ...
Page 523
The estimated durations and costs of these activities are shown below in the left
column . 10.6-2 . * The P - H Microchip Co. needs to undertake a major
maintenance and renovation program to overhaul and modernize its facilities for
wafer ...
The estimated durations and costs of these activities are shown below in the left
column . 10.6-2 . * The P - H Microchip Co. needs to undertake a major
maintenance and renovation program to overhaul and modernize its facilities for
wafer ...
Page 571
Id = Icons m = maximize the total estimated increase in the plurality ... Based on
polling information , an estimate has been made of the number of additional
votes that can be won in the different broadcasting areas depending upon the
number ...
Id = Icons m = maximize the total estimated increase in the plurality ... Based on
polling information , an estimate has been made of the number of additional
votes that can be won in the different broadcasting areas depending upon the
number ...
What people are saying - Write a review
User Review - Flag as inappropriate
i
User Review - Flag as inappropriate
I want review this book
Other editions - View all
Common terms and phrases
activity additional algorithm allocation allowable amount apply assignment basic solution basic variable BF solution bound boundary called changes coefficients column complete Consider constraint Construct corresponding cost CPF solution decision variables demand described determine distribution dual problem entering equal equations estimates example feasible feasible region feasible solutions FIGURE final flow formulation functional constraints given gives goal identify illustrate increase indicates initial iteration linear programming Maximize million Minimize month needed node nonbasic variables objective function obtained operations optimal optimal solution original parameters path plant possible presented primal problem Prob procedure profit programming problem provides range remaining resource respective resulting revised shown shows side simplex method simplex tableau slack solve step supply Table tableau tion unit values weeks Wyndor Glass zero